CASE STUDY

DUNCAN PUBLIC

SCHOOLS

Drywall finishing and painting system for new gypsum board and brick walls

LOCATION

700 E Chestnut Ave, Duncan, OK 73533

CLIENT

HopeBuilds Construction

PROJECT OVERVIEW

Finishing a School Project on a Tight Back-to-School Schedule

DRL Coatings completed drywall finishing and painting work for Duncan Public Schools in Duncan, Oklahoma. The scope included approximately 13,000 SF of new gypsum board walls, 4,000 SF of brick walls, and the painting of hollow metal doors and frames using PPG coatings.

and close coordination between the tape and bed and painting crews to keep the work moving without compromising quality or safety.

Gypsum Board Walls

13,000 SF

Tape and bed and painting system for new gypsum board walls.

brick Walls

4,000 SF

Painting system applied to brick wall surfaces.

Doors & Frames

Hollow Metal

Painting system for hollow metal doors and frames.

THE CHALLENGE

Back-to-School Deadline

The primary challenge was completing the project within a tight schedule driven by students returning to school.

The work had to move efficiently across the drywall finishing and painting phases while maintaining quality, production efficiency, and safe working conditions.

OUR SOLUTION

Coordinated Trade Execution

DRL Coatings utilized a specialized crew with adequate manpower to maintain the production pace required by the accelerated schedule.

Strong coordination between the tape and bed and painting trades allowed each phase to progress efficiently and helped ensure the full scope was completed without impacting the required delivery schedule.

THE RESULT

The project was completed and delivered on schedule with zero safety incidents. Despite the accelerated timeline, the client had no concerns regarding the schedule, and additional Change Order work was successfully completed without affecting the original completion date.

ON SCHEDULE

Project completed and delivered as planned

0

Safety Incidents

CHANGE ORDERS

Additional work completed without impacting the original schedule

PROJECT GALLERY

Visual documentation.

INTERIOR PAINTED GYPSUM WALLS
BRICK WALLS
LEVEL 4 DRYWALL FINISH
MULTIPLE SUBSTRATE
PAINTING OF HM DOORS & FRAMES
INTERIOR PAINTED GYPSUM WALLS
PAINTING OF EXTERIOR HM DOORS

“This project demonstrates how careful manpower planning and coordination between trades can keep an accelerated construction schedule moving without compromising safety or delivery.”